Monday, June 4, 2012

Sold! (again)

Yup! It's happened!

We had three private showings of our current home this past week;  one on Wednesday, one on Thursday, and one on Friday. The couple who came thru our house on Saturday made us an offer that afternoon. 
We amended the offer to change the closing date from late July to August 21.... they accepted it by noon today. What that means for us is that they're allowing us to stay living in this house until our new home is ready to move into on the 20th. That's huge!

So we cancelled the open house we had planned today. I saw at least 4 cars stop out at our driveway (one person came up and knocked on the door even) that apparently were planning on attending the open house.

So that's the big exciting news for the weekend for us! :)  Now we can focus on construction of our new home and not worry about working to sell this one.

Speaking of our new home, Friday's progress had several substantial things take place.

As you can see in the following photo, pretty much all the windows are now in place. The notable exceptions are the front entry window and the backside top window in the Wall of Windows. Both of those have arched tops, so that must have something to do with them not being installed yet.


The bathtub for the girls' bathroom upstairs was delivered to the site on Friday as well...


In the next photo of the living room you may recognize the piece of paper nailed to the wall. I mentioned in my last blog post that it is the drawing of how that wall is going to be framed.... the part of that photo that is new is above the fireplace.


There are going to be three "nooks" above the fireplace on that wall. Each will be about 20" deep and will have a small can light in the arch at the top.



Also on Friday, the installer from the cabinet company was on-site. He went through the entire house measuring things up (and drawing them on the plywood floors with labels on them) so that the cabinet makers can begin building our cabinets. This photo is of the floor markings in the kitchen, with the raised "snack bar" on the kitchen counter.


Rachel's bedroom window got installed on Friday.....


....as did the smallest window in the house (bonus room).


This rather odd looking photo is taken from down in the laundry room looking up, through the trusses, to an opening in the wall above from the hallway to the future bonus room.


That opening is going to be one of four "attic access hatches" in the house. The builder has to have access to all attic spaces in the entire place. When Robin and I were walking past this opening upstairs in the hallway we looked at it and both said "laundry chute" at the same time. So I called the builder right then and there and asked him about the possibility of adding that in. In the photo above the chute would go just to the right side of the hatch opening shown, and right down in between those two roof trusses shown there.
He said he could do it, and that we'd need to talk to the cabinet supplier (which we just happened to have a meeting on Saturday anyway) about changing one cabinet to accommodate the bottom end of the chute.

So while the private showing was going on yesterday (Saturday), Robin and I were up in Green Bay having our final meeting with the cabinet supplier. We had to pick out our laminate countertops and the door/drawer hardware for all the cabinets. While we were there we told her about our idea of a laundry chute. She gave us some ideas on how to make the cabinets below work and then said she'd throw that in without any additional charge for the cabinets (yay!).

We then left there and went the other side of Green Bay to select our granite for the kitchen countertops. The photo below shows the granite (it's outside in the bright sunlight, so it's a bit washed out) with our paint color for the walls and the cabinet sample.


Monday is our big contractor walkthrough at the site. Dennis, our builder, and pretty much all of the sub-contractors will be there for questions, answers, etc. Pretty much anything any of us come up with.
Then Tuesday we'll be meeting at the bank to close on our construction loan so all the subs who've already done work on the house can finally get paid.

Paul

Thursday, May 31, 2012

A little, but alot....

I hope everyone had a good long weekend....

Since the end of last week there's been alot going on at the house, but not much all that readily visible nor able to be easily photographed.

I'm going to combine a few days photos into this one post simply because there aren't alot of photos of things before today's progress. As you see the photos for the last few days you'll understand why.

As you may recall they began putting the shingles on the roof late last week.... well, they finally finished that part of the process yesterday...

progress on the shingles as of the end of last week

shingles above the master bedroom 


the shingles as of Tuesday
The shingles are all finished as of Thursday!
Some other very notable bits of progress that have happened this week include the "walling off" (via the vapor barrier "wrap") of the bonus room...



..and a couple other areas around various attic spaces.

the attic space above the master bedroom
Also, on Tuesday we were pleasantly surprised to find that the carpenters had installed the temporary stairway down to the basement. The stud walls you see around the staircase down in the basement will have two doors at the bottom;  one at the bottom of the stairs themselves, and another closing off the storage space underneath the stairs themselves.



On Saturday we went out there for a couple of hours. I had to bring out the chainsaw and cut out alot of brush and some very small trees so the excavator could finish the grading on the site.... For a period of time, Rachel was put in charge of the camera and taking the pictures:

Lyndsey hanging out at her bedroom window
..and this is what happens when Rachel is unsupervised while roaming around with the camera....




yeah, the little turkey figured out the timer on the camera all by herself!

On Wednesday we noticed that the pocket door frames had been installed... one in each of the bedroom closets, one in each bathroom. The frame for the pocket doors is the part where you can see all of the horizontal framing in the midst of all the vertical framing. The pocket door then slides in between those horizontal members.


 
Also on this same day we also found out that they built a temporary stairway down from the garage to the basement. These will eventually be replaced by a permanent concrete stairway (I believe at the same time they pour the garage slab)


Today, however, was a huge day in the progress of our new home. After a literal flurry of phone calls this morning between the builder, Robin, and I to make various decisions on framing items (fireplace, tray ceiling, etc) that will be worked on by the end of this week, the day settled down to more "normal" happenings, with us anxiously awaiting to see what progress was made today.  It was a step we've been waiting for for a while now and we weren't disappointed at all!..... windows!

The house has to be all "buttoned up" before Monday's contractor walkthrough meeting and to that end, the windows and doors showed up on site. Most of the windows are now installed. None of the doors are yet, but almost all of them are on-site waiting to be installed tomorrow.


The following are some closer-up photos around the outside of the house. You can see we're using the Marvin "Integrity" line of windows. They're a notch less expensive than the Anderson windows originally in the contract, but are actually rated higher in quality by Consumer Reports for things like insulation value, hardware quality, etc. You can see the grills in the windows. We opted for these to be installed in all the windows facing the front of the house. The grills are set inside the window itself, between the two panes of glass. All the operable windows are casement style, with any operable transom windows (the smaller panes of glass either above larger panes of glass, or smaller rectangles of glass set up high are called "transoms") being an "awning" style (meaning they are hinged on the top of the glass rather than the sides like a regular casement)



The den and master bedroom windows are in place
(from left to right) master bedroom reading nook (1), master bathroom (3), transoms in the living room (2)

Robin's "wall of windows", the patio doors, Lyndsey's room, and kitchen


laundry room, bonus room, garage
The front entry door showed up on-site today as well.... it will have to be painted in the future (we haven't decided on the color yet), but for now they'll install it unpainted.

front door - exterior view (it's inside the house leaning up against a wall now)

front door - interior view
The carpenters also began framing up the area in the living room where the fireplace will go. If you look closely in the next photos you can see a piece of paper containing a computer drawing of what that wall will look like stuck up on the framing, complete with dimensions, that the carpenters are using to frame up that wall. 
The boxed in area in the middle is the fireplace.. you can see the two transom windows flanking it on both sides, and just below each of those transoms will be a built-in cabinet with shelving.



Up next are some photos of some of the windows as seen from the inside of the house.

patio doors

a closeup of part of the "Wall of Windows"

Lyndsey's window

bonus room
Also today the plumbing fixtures for the upstairs bathroom/vanities arrived from Home Depot... while the most crucial piece of that delivery was the shower valve (the plumber will be installing it Monday morning during rough-ins), the part that we really needed to verify was that the faucets are tall enough to fit over the girls' vessel sinks.
We chose a "brushed nickel" finish for the upstairs bathroom fixtures and selected a series of fixtures and accessories (towel bars, paper holder, etc) called "Bamboo". (we were fortunate enough to, after a ton of searching, find faucets the girls love for an inexpensive price) The faucets are of the type where the water doesn't come out of a hole in the bottom of the spout, but rather flows out over the top edge of the spout into the bowl.

Lyndsey's sink and faucet

Rachel's sink and faucet

Next up for Robin and I... 
Tomorrow the rest of the windows and some of the doors should be installed, the fireplace "black box" should be in place, and there may be a bathtub in the upstairs bathroom as well.

This weekend Robin and I have to travel back up to Green Bay where we'll make our final selections on countertops (laminate) and cabinet hardware. Then we'll travel to the opposite side of Green Bay to make our selection for the granite countertops for the kitchen.

All this progress in the construction of the new house isn't meant to overshadow the things going on with the sale of our current house.

Two Sundays ago you may recall we had our first open house since this house went back on the market. Well, in there we've had Memorial Day weekend, so we've been hoping that kind of thing is the reason there's not been much for private showings (the first go-around on the market we had a ton of private showings in addition to the open houses).
Well, we had our first private showing Wednesday morning... the feedback on that was was "somewhat interested", but that they had another house they liked better so far.
We now have another private showing tomorrow afternoon, and yet another private showing Saturday morning (at the same time we'll be in Green Bay).
Also we have our second open house this coming Sunday as well.... we're hopeful an offer comes out of one of these showings! :)

Once we get our meetings done on Saturday, the only supplier meeting we'll have left is lighting. We have some ideas on what we want, and we've looked around somewhat a couple of different times at different places, but haven't met with the supplier yet.

Monday is the big contractor walkthrough on-site. Most every sub-contractor will be there at some point during the day. Robin and I will be there most of the day as well. Discussing details with the various suppliers and our builder.
Tuesday morning we will (finally) actually close on our construction loan. It's kind of weird not closing on it until this far into construction, but the bank pulled alot of strings to allow construction to start prior to closing so that Dennis could get an entry in this summer's Parade of Homes (if we would have had to wait for closing before starting he would never have made the Parade).

Things are certainly keeping us hopping, that's for sure!

Paul

Saturday, May 26, 2012

Time for a roof!

The last few days we've seen them begin to put the finished roof on....

First up was the tar paper that lays underneath the roofing shingles. 



Robin looking down over the newly installed front porch trusses




While the tar paper was going on the roof, the framers were also finishing up the truss work. At this same time they also added the plywood subflooring in the future bonus room (that's about as far toward "finished" that the builder will take it, once it's all enclosed).



Robin climbing around in the roof trusses over the garage

Thursday saw the roof shingles begin to go up on the roof. They have numerous packages of shingles sitting up there waiting to be nailed down and they began on the west side (master bedroom) side of the roof. Alot of the back side shingles are in place too.



With our contractor walkthrough looming on June 4th we've come to realize that that means they'll have to have the house all "buttoned-up" by then;  that means the doors and windows will be in place so that they can lock the house up while the interior work is being done for the next 2-3 months.

The next week should see alot of changes!

I hope everyone has a good holiday weekend!

Paul